Three Minute Update: November 13, 2012

There are many technology projects currently under way in the District.  Richard Hernandez has summarized the status of those that were recently completed, as well as those with an anticipated completion date in the near future.  These are:

  • Installation and Configuration of Cisco 3560X 10/100/1000 for expanded Firewall and Internet throughput – Completed October 5, 2012
  • Planned BGP configuration and upgrade from 50MB to 300MB Pipe for Internet Services -Completed mid-October, 2012
  • Installation and Configuration of POE Blade Module for Cisco 4506 Router at Lakewood – Completed October 10, 2012
  • Installation and Configuration of POE Blade Module for Cisco 4506 Router at Congers – Completed October 11, 2012
  • Installation and Configuration of 4 additional Virtual Servers for Gmail Migration and Mail Relay – Completed October 12, 2012
  • Installation and Configuration of POE Switch in Bardonia Lab – Completed October 15, 2012
  • Installation and Configuration of POE Switch in New City Lab – Completed October 16, 2012
  • Installation and Configuration of POE Switch in Laurel Plains 2nd Wiring Closet – Completed October 17, 2012
  • Installation and Configuration of POE Switch in West Nyack Lab – Completed October 18, 2012
  • South TV Studio re-wiring and installation and configuration of Gigabit Switch – Completed October 18, 2012
  • Stage 1 of installation of New Cisco Wireless AP’s for 3rd, 4th, 5th Grade Sections – currently in progress
  • Stage 2 of upgrading existing elementary wireless to New Cisco AP’s – tentatively scheduled to begin November 13, 2012
  • Continuation of wireless upgrades (delayed by Hurricane Sandy) for Festa A-Wing and C-Wing – to begin November 13, 2012
  • Apple Lab installation services (Switch Technologies) tentatively scheduled for November 13 thru 15 for South Art Lab, North Music Lab.  This was rescheduled due to the storm.
  • Implementation of Cisco NCS Management Software for management of  Wireless APs, Switches, Routers – tentatively scheduled for November 14, 2012
  • Wireless upgrades to N – Access Points for Festa D-Wing – delayed by Hurricane Sandy – tentatively scheduled for November 19, 2012